01536 48433338b Telford Way, Kettering
CPL
News17 Feb 2025

Twenty-unit fleet build for Yorkshire Water

Twenty-two vans. One workshop. Six weeks. When Yorkshire Water's fleet team asked CPL to build a standardised access-platform fleet on a tight calendar — same chassis, same livery, same sign-off — it was exactly the kind of programme our Kettering shop is set up for.

ClientYorkshire Water
Units delivered22
ChassisFord Transit 350
Platform12 m van-mounted MEWP
Programme length6 weeks · 3 phased waves
Snags raisedZero

Overview

Yorkshire Water operates infrastructure that serves more than 3.7 million customers across the region. Their field teams work at height every day — inspecting reservoirs, maintaining overhead cable runs, accessing pump stations on mixed terrain. The existing fleet had aged into a patchwork of hired units and owned vehicles of varying spec and condition.

The procurement team approached CPL having already done their homework. They knew they wanted a van-mounted MEWP at 12 m working height on a Ford Transit chassis. What they needed was a single supplier who could deliver consistency at scale — same loadout, same livery, same sign-off standard — across twenty-two units, within a quarter.

What we built

Every unit left the Kettering yard to an identical spec, signed off by the same approved engineer. The build sheet covered:

  • Ford Transit 350 L4H3 chassis, automatic gearbox, 170 hp diesel
  • 12 m working height, 6.0 m outreach, 200 kg basket capacity
  • Four-point independent outriggers with custom wide steel bearing plates
  • 360° continuous slewing, twin-load-cell overload monitoring
  • Yorkshire Water full-wrap livery with PAS 43 hi-vis chevron rear panel
  • Rear-mounted 25 m cable reel rated to 16 A · 240 V shore-power socket
  • Integrated tool tray, beacon array, LED work-light pair
  • 12-month CPL Care: annual service, 24-hour breakdown cover, IPAF re-validation

The outrigger choice was the single biggest engineering call on the brief. Yorkshire Water's field experience pointed to consistent issues with rubber-pad outriggers at soft-ground pump station access points. We agreed a wider steel bearing-plate design, plasma-cut in house to the customer's drawing, that drops ground bearing pressure by approximately 40% at full extension.

Dispatch morning at the Kettering yard — the first six units of the twenty-two-vehicle programme, identically specced and ready for handover.

How we did it

Twenty-two builds inside six weeks needed phasing. Chassis arrived from Ford on a staggered delivery against an agreed schedule, and we ran two parallel build lanes through Kettering: wave one (six units), wave two (eight), wave three (eight). Each wave moved through four stations in sequence:

  1. Chassis preparation. Subframe reinforcement, wiring loom extension for the MEWP control circuit, rear work-lighting bar fit.
  2. Platform fit and outrigger fabrication. Platform units arrived from our KLUBB Group partners on a matched schedule. Trial-fit, alignment, torque to spec, then outrigger legs welded and bearing plates plasma-cut to drawing.
  3. Load and function test. Every unit run through a full cycle — platform at max height and reach, outriggers on simulated soft ground, basket-load overload trip.
  4. Livery and IPAF sign-off. Full-wrap livery applied in-house. IPAF inspection by our approved engineer before dispatch.

Keeping livery in-house was the unlock that made the timeline work. External bodyshops typically add 7–10 working days to a build slot; doing it ourselves means we can sequence wrap immediately behind load-test, with no waiting and no transport movements.

On-site at a Yorkshire Water access point — wide steel bearing-plate outriggers in place on grass, ground bearing pressure reduced by approximately 40% versus standard rubber-pad spec.
“Twenty-two identical units, delivered on the dates we agreed, with no snags raised at incoming inspection. The CPL team understood what a fleet programme actually needs — not just twenty-two builds, but twenty-two consistent builds.”
Fleet Manager · Yorkshire WaterIllustrative quote · pending customer sign-off

Results

  • 22 of 22 units passed incoming inspection. Zero snags raised.
  • 6 weeks end-to-end against an initial 8-week customer target.
  • Phased deliverymatched Yorkshire Water's fleet rotation, so old vehicles came off the road as new ones came on.
  • 40% reduction in ground bearing pressure at the outriggers versus standard rubber-pad spec, on the equivalent platform load.
  • 12 months of CPL Careactivated on day-of-dispatch — covered service and breakdown across the fleet's first year in operation.

If you're planning a similar programme — fleet replacement, standardised spec, single supplier — get in touch. We can run a build schedule alongside finance pre-approval so the units ship ready to deploy, in a wave pattern that matches your operational handover.